We always believe that one's character decides products' quality, the details decides products' high-quality ,together with the REALISTIC,EFFICIENT AND INNOVATIVE crew spirit for Copper Extrusion Machine, Galvanized Wire, Electromagnetic Wire Taping Machine, We are looking forward to establishing long-term business relationships with you. Your comments and suggestions are highly appreciated.
Newly Arrival Hot Dip Steel Wire Galvanization Line - Steel Wire & Rope Closing Line PengSheng Detail:
Main technical data
No.
Model
Number
of bobbin
Rope size
Rotating
Speed
(rpm)
Tension
wheel
size
(mm)
Motor
power
(KW)
Min.
Max.
1
KS 6/630
6
15
25
80
1200
37
2
KS 6/800
6
20
35
60
1600
45
3
KS 8/1000
8
25
50
50
1800
75
4
KS 8/1600
8
50
100
35
3000
90
5
KS 8/1800
8
60
120
30
4000
132
6
KS 8/2000
8
70
150
25
5000
160
Product detail pictures:
Related Product Guide:
We have been proud from the higher consumer gratification and wide acceptance due to our persistent pursuit of high quality both on product or service and service for Newly Arrival Hot Dip Steel Wire Galvanization Line - Steel Wire & Rope Closing Line PengSheng , The product will supply to all over the world, such as: Sheffield, Sri Lanka, Algeria, Our products are widely sold to Europe, USA, Russia, UK, France, Australia, Middle East, South America, Africa, and Southeast Asia, etc. Our solutions are highly recognized by our customers from all around the world. And our company is committed to continually improving effectiveness of our management system to maximize customer satisfaction. We sincerely hope to make progress with our customers and create a win-win future together. Welcome to join us for business!
Good quality and fast delivery, it's very nice. Some products have a little bit problem, but the supplier replaced timely, overall, we are satisfied. By Marcy Real from Sao Paulo - 2018.09.19 18:37
As a veteran of this industry, we can say that the company can be a leader in the industry, select them is right. By Laura from Madagascar - 2018.10.31 10:02
Features
● Forged or casted capstan with hardness of HRC 58-62.
● High efficiency transmission with gear box or belt.
● Movable die box for easy adjustment and easy die changing.
● High performance cooling system for the capstan and die box
● High safety standard and friendly HMI control system
Available options
● Rotating die box with soap stirrers or rolling cassette
● Forged capstan and tungsten carbide coated capstan
● Accumulation of first drawing blocks
● Block stripper for coiling
● Fi...
Principle
The principle of continuous cladding/sheathing is similar with that of continuous extrusion. Using tangential tooling arrangement, the extrusion wheel drives two rods into the cladding/sheathing chamber. Under the high temperature and pressure, the material either reaches the condition for metallurgical bonding and forms a metal protective layer to directly clad the metal wire core that enters the chamber (cladding), or is extruded through the space between mandrel and cavity die t...
● Heavy duty machine with nine 1200mm blocks
● Rotating type pay-off suitable for high carbon wire rods.
● Sensitive rollers for wire tension control
● Powerful motor with high efficiency transmission system
● International NSK bearing and Siemens electrical control
Item
Unit
Specification
Inlet wire Dia.
mm
8.0-16.0
Outlet wire Dia.
mm
4.0-9.0
Block size
mm
1200
Line speed
mm
5.5-7.0
Block motor power
KW
132
Block cooling type
Inner water...
Pay-offs
Hydraulic vertical pay-off: Double vertical hydraulic rod stems that easy for wire loaded and capable of continuous wire decoiling.
Horizontal pay-off: Simple payoff with two working stems that suitable for the high and low carbon steel wires. It could load two coils of rod that realize the continuous wire rod decoiling.
Overhead pay-off: Passive type pay-off for wire coils and equipped with the guiding rollers to avoid any wire disordered.
Spool pay-of...
Principle
The principle of continuous cladding/sheathing is similar with that of continuous extrusion. Using tangential tooling arrangement, the extrusion wheel drives two rods into the cladding/sheathing chamber. Under the high temperature and pressure, the material either reaches the condition for metallurgical bonding and forms a metal protective layer to directly clad the metal wire core that enters the chamber (cladding), or is extruded through the space between mandrel and cavity die t...